After a late September 2010 flood covered over 75% of the ground floor of The Plaza at King of Prussia, Scungio Borst was called in to manage the damage reconstruction work of all common areas and over 30 tenants plus the Food Court.
In total over $4,000,000 of work was completed in 54 calendar days, preparing the mall for the busy holiday season. With regards to the food court, after flood remediation, we demolished, abated, raised a concrete slab, reconfigured restrooms, prepared a clean and fresh food court and met the obligation to open it for “Black Friday” 2010 while preparing the food court for an early 2011 complete renovation.

Project Owner

Kravco Simon

Project Value

$5,500,000

Project Details

After a late September 2010 flood covered over 75% of the ground floor of The Plaza at King of Prussia, Scungio Borst was called in to manage the damage reconstruction work of all common areas and over 30 tenants plus the Food Court.
In total over $4,000,000 of work was completed in 54 calendar days, preparing the mall for the busy holiday season. With regards to the food court, after flood remediation, we demolished, abated, raised a concrete slab, reconfigured restrooms, prepared a clean and fresh food court and met the obligation to open it for “Black Friday” 2010 while preparing the food court for an early 2011 complete renovation.

Project Owner

Kravco Simon

Project Value

$5,500,000